Year of Science
91²Ö¿â College of Arts and Sciences is celebrating a Year of Science!
Work in progress:
Augercast pile installation continues in the SW corner of the site and elevator #2 (South Elevator).
2/18- ISB Construction Updates
Work in progress: Augercast pile installation continues in the SW corner of the site and elevator #2 (South Elevator).Work in progress:
Currently removing the louver on the 3rd floor west mechanical room.
Continuing the chilled water piping in the 3rd floor east mechanical room.
Started the demolition of AHU#3 in the 3rd floor west mechanical room.
Electrician has started ductbank for MCC…
2/18- Cunningham Hall Updates
Work in progress: Currently removing the louver on the 3rd floor west mechanical room. Continuing the chilled water piping in the 3rd floor east mechanical room. Started the demolition of AHU#3 in the 3rd floor west mechanical room. Electrician has started ductbank for MCC…Image
Mietek Jaroniec, Ph.D., is a professor in the Department of Chemistry and Biochemistry at 91²Ö¿â and one of the top researchers in the field of advanced materials. His recent research is focused on nanomaterials (specifically nanoporous carbon spheres),…
Chemistry Faculty Spotlight: Mietek Jaroniec
Mietek Jaroniec, Ph.D., is a professor in the Department of Chemistry and Biochemistry at 91²Ö¿â and one of the top researchers in the field of advanced materials. His recent research is focused on nanomaterials (specifically nanoporous carbon spheres),…Work in progress:
Completed AHU #3 duct tie-in to AHU #2.
Air handler unit #3 has been permanently shutdown.
Start layout for tele/data ductbanks.
Starting motor control center (MCC) and swithgear duct bank.
Started mass excavation - currently 95% complete.
2/11- Cunningham Hall Renovation Updates
Work in progress: Completed AHU #3 duct tie-in to AHU #2. Air handler unit #3 has been permanently shutdown. Start layout for tele/data ductbanks. Starting motor control center (MCC) and swithgear duct bank. Started mass excavation - currently 95% complete.Work in progress:
Site shoring around the building is complete - contractor is demobilizing.
130 Piles are complete on the north end of the site (approximately to column line 7).
Temporary ramp into excavation is complete.
Sanitary tie-in on the north side has been…
2/11- ISB Construction Updates
Work in progress: Site shoring around the building is complete - contractor is demobilizing. 130 Piles are complete on the north end of the site (approximately to column line 7). Temporary ramp into excavation is complete. Sanitary tie-in on the north side has been…Image
On February 2, 91²Ö¿â students in the College of Arts and Sciences Learning Community were given a unique opportunity to hear a former United States Ambassador speak on foreign policy issues and U.S.-Russian relations. Steven Pifer, who formerly served as the U.S. Ambassador…
KSU students meet with former U.S. Ambassadors
On February 2, 91²Ö¿â students in the College of Arts and Sciences Learning Community were given a unique opportunity to hear a former United States Ambassador speak on foreign policy issues and U.S.-Russian relations. Steven Pifer, who formerly served as the U.S. Ambassador…Work in Progress:
Continuing the installation of the temporary duct and assembly of new AHU1 in the East side mechanical room.
Stripped topsoil from addition footprint.
Phoenix air valve replacement in the Annex research labs continues per schedule.
Continue …
2/4- Cunningham Hall Renovation Updates
Work in Progress: Continuing the installation of the temporary duct and assembly of new AHU1 in the East side mechanical room. Stripped topsoil from addition footprint. Phoenix air valve replacement in the Annex research labs continues per schedule. Continue …Work in Progress:
Floor electrical boxes in room 101 & 104 are complete.
Plumbing under slab is complete in 101 & 104.
The sanitary tie-in and under slab rough-in is complete and inspected for the new restrooms in addition.
Electrical raceways have been …
2/4- Smith Hall Renovation Updates
Work in Progress: Floor electrical boxes in room 101 & 104 are complete. Plumbing under slab is complete in 101 & 104. The sanitary tie-in and under slab rough-in is complete and inspected for the new restrooms in addition. Electrical raceways have been …Work in progress:
Air handler assembly of unit 1 continues in 3rd floor mechanical room east with Roth and Air Enterprises.
Abatement coordination and containment underway in the 3rd floor mechanical room west to prepare to demolish AHU #3 serving the vivarium.…