News
Work in Progress
Complete drywall work in basement, Human Anatomy Lab.
Taping in Human Anatomy Lab is in progress.
Continue north side corridor curtain wall installation.
Continue cleaning operations.
Looking Forward
Continue detailing work in basement, Human Anatomy…
ISB
Work in Progress
Brick work along line 17, from B to G is in progress.
Continue retaining wall along line 8.
Continue curtain wall installation at the northeast side.
Finalize pre cast and brick work along A line.
Continue the pouring of the hydraulic slab on the…
Work in Progress
Continue sidewalk pouring and paver’s installation.
Continue installation of stair treads ADA addition.
Continue carpet installation.
Complete duct work roughed in Human Anatomy Lab.
Continue north side corridor curtain wall installation.
Start cleaning…
ISB
Work in Progress
Continue the work of water proofing mud mat on the east side of the building, lines 14 to 17.
Continue framing roof work at east side of the building, and roofing work on the penthouse.
Continue curtain wall installation at the northeast side.…
Image
Four 91²Ö¿â graduate students in the Department of Psychological Sciences, in the College of Arts and Sciences, won the Sloboda and Bukoski Cup at the Society for Prevention Research’s annual conference.
Liz Baker, Karly Cochran, Haylee DeLuca and Logan Stigall…
The Glenn H. Brown Liquid Crystal Institute® in the College of Arts and Sciences at 91²Ö¿â will host the 26th International Liquid Crystal Conference on the Kent Campus from July 31-Aug. 5. The event is open to the public, but paid registration is required.
A group of researchers in 91²Ö¿â's College of Arts and Sciences have published a breakthrough article on new properties of liquid crystals in the May 27 issue of Physical Review Letters. The article, which describes some recent surprising results involving…
Work in Progress:
Duct work on the 3rd floor is about 30% complete.
Duct pressure testing is underway.
Electrical disconnect and make safe are underway for the AHU's above the penthouse.
Working on the steam pipe relocation on the second floor.
Plumbing isolation valve…
Work in progress:
Temporary steam condensate line in tunnel is complete along with taps on main condensate and steam feeds for future connections.
Chilled water line hangers are being installed above AHUs in Williams mechanical room.
Steel erection in sequence 4 & 5.…
Work in Progress:
Forming basement retaining wall from column line 13G to 17C in progress.
Forming of lift #2 at elevator #2 (south) for second pour is in progress.
Forming of stair #3 is in progress.
Concrete piers along column line B are in progress.
Steel erection of…